PMP Actual Exam Questions
1 / 995
What is the definition of project risk management planning?
2 / 995
What is the definition of project communication planning?
This ensures that the communication plan is tailored to facilitate effective information exchange among project stakeholders.
3 / 995
What is the definition of project stakeholder analysis?
Explanation: Stakeholder analysis is a critical process in project management that helps the project manager and team identify the stakeholders, understand their interests, influence, and expectations, and determine how to engage and communicate with them effectively. This analysis ensures that stakeholder needs are addressed throughout the project lifecycle.
4 / 995
What is the definition of project stakeholder engagement?
5 / 995
What is the definition of project procurement control?
6 / 995
What is the definition of project change control?
7 / 995
What is the definition of project risk register?
8 / 995
What is the definition of project stakeholder register?
9 / 995
What is the definition of project procurement documents?
10 / 995
What is the definition of project quality control?
11 / 995
What is the definition of project cost baseline?
12 / 995
What is the definition of project schedule network diagram?
13 / 995
What is the definition of project schedule?
14 / 995
What is the definition of project network diagram?
15 / 995
What is the definition of work breakdown structure (WBS)?
16 / 995
What is the definition of project scope statement?
17 / 995
What is the definition of project charter?
18 / 995
What is the definition of project management plan?
19 / 995
What is the definition of project stakeholder management?
20 / 995
What is the definition of project procurement management?
21 / 995
What is the definition of project risk management?
22 / 995
What is the definition of project communications management?
23 / 995
What is the definition of project resource management?
24 / 995
What is the definition of project quality management?
25 / 995
What is the definition of project cost management?
26 / 995
What is the definition of project schedule management?
27 / 995
What is the definition of project scope management?
28 / 995
What is the definition of project integration management?
29 / 995
What is the definition of project management?
30 / 995
What is the definition of a project life cycle?
31 / 995
What is the definition of a project management office (PMO)?
32 / 995
What is the definition of a portfolio?
33 / 995
What is the definition of a program?
34 / 995
What is the definition of a project?
35 / 995
What is the purpose of a project risk register?
36 / 995
What is the purpose of a project schedule baseline?
37 / 995
What is the purpose of a project quality baseline?
38 / 995
What is the purpose of a project scope baseline?
39 / 995
What is the purpose of a project cost baseline?
40 / 995
What is the purpose of a project resource calendar?
41 / 995
What is the purpose of a project change log?
42 / 995
What is the purpose of a project issue log?
43 / 995
44 / 995
What is the purpose of a project status report?
45 / 995
What is the purpose of a project lessons learned report?
46 / 995
What is the purpose of a project closure plan?
47 / 995
What is the purpose of a project change management plan?
48 / 995
What is the purpose of a project human resource management plan?
49 / 995
What is the purpose of a project stakeholder management plan?
50 / 995
What is the purpose of a project procurement management plan?
51 / 995
What is the purpose of a project quality management plan?
52 / 995
What is the purpose of a project communication plan?
53 / 995
What is the purpose of a project risk management plan?
54 / 995
What is the purpose of a project cost estimate?
55 / 995
What is the critical path in a project network diagram?
56 / 995
What is the purpose of a project schedule?
57 / 995
What is a project milestone?
58 / 995
What is the purpose of a work breakdown structure (WBS)?
59 / 995
What is the purpose of a project scope statement?
60 / 995
What is a project constraint?
61 / 995
What is a stakeholder?
62 / 995
What is the purpose of a project charter?
63 / 995
64 / 995
65 / 995
Which of the following is not a tool or technique of the Develop Project Charter process?
66 / 995
Which of the following is not an output of the Develop Project Charter process?
67 / 995
What is the purpose of the Develop Project Charter process?
68 / 995
Which of the following is not a tool or technique of the Close Project or Phase process?
69 / 995
Which of the following is not an output of the Close Project or Phase process?
70 / 995
What is the purpose of the Close Project or Phase process?
71 / 995
Which of the following is not a tool or technique of the Perform Integrated Change Control process?
72 / 995
Which of the following is not an output of the Perform Integrated Change Control process?
73 / 995
What is the purpose of the Perform Integrated Change Control process?
74 / 995
Which of the following is not a tool or technique of the Monitor and Control Project Work process?
75 / 995
Which of the following is not an output of the Monitor and Control Project Work process?
76 / 995
What is the purpose of the Monitor and Control Project Work process?
77 / 995
Which of the following is not a tool or technique of the Direct and Manage Project Work process?
78 / 995
Which of the following is not an output of the Direct and Manage Project Work process?
79 / 995
What is the purpose of the Direct and Manage Project Work process?
80 / 995
Which of the following is not a tool or technique of the Develop Project Management Plan process?
81 / 995
Which of the following is not an output of the Develop Project Management Plan process?
82 / 995
What is the purpose of the Develop Project Management Plan process?
83 / 995
84 / 995
85 / 995
86 / 995
87 / 995
88 / 995
89 / 995
Which of the following is not a project integration management knowledge area process?
90 / 995
Which of the following is not an input to the Develop Project Management Plan process?
91 / 995
What is the last step in project integration management?
92 / 995
93 / 995
Which of the following is an output of the Develop Project Management Plan process?
94 / 995
What is the first step in project integration management?
95 / 995
What is the main purpose of a project stakeholder register?
96 / 995
97 / 995
Which of the following is an example of a project assumption?
98 / 995
What is the main purpose of a project communication log?
99 / 995
100 / 995
101 / 995
What is the main purpose of a project lessons learned report?
102 / 995
103 / 995
104 / 995
What is the main purpose of a project status report?
105 / 995
106 / 995
Which of the following is an example of a project risk?
107 / 995
What is the main purpose of a project lessons learned log?
108 / 995
109 / 995
Which of the following is NOT a project management process group?
110 / 995
Which of the following is an example of a project output?
111 / 995
What is the main purpose of a project change log?
112 / 995
113 / 995
Which of the following is an example of a project constraint?
114 / 995
What is the main purpose of a project issue log?
115 / 995
116 / 995
Which of the following is NOT a stage of the project life cycle?
117 / 995
Which of the following is an example of a project deliverable?
118 / 995
What is the main purpose of a project risk register?
119 / 995
120 / 995
Which of the following is an example of a project input?
121 / 995
What is the main purpose of a project stakeholder analysis?
122 / 995
123 / 995
Which of the following is NOT a project constraint?
124 / 995
125 / 995
What is the purpose of a schedule management plan?
126 / 995
What is the purpose of a scope management plan?
127 / 995
What is the purpose of a risk management plan?
128 / 995
What is the purpose of a change management plan?
129 / 995
What is the purpose of a stakeholder engagement plan?
130 / 995
What is the purpose of a human resource management plan?
131 / 995
What is the purpose of a procurement management plan?
132 / 995
What is the purpose of a quality management plan?
133 / 995
What is the purpose of a communication plan?
134 / 995
What is the purpose of a stakeholder register?
135 / 995
What is the purpose of a risk register?
136 / 995
What is the purpose of a project management plan?
137 / 995
What is the purpose of a project closure report?
138 / 995
What is the purpose of a lessons learned report?
139 / 995
140 / 995
What is the purpose of a change control process?
141 / 995
What is a project issue?
142 / 995
What is a project risk?
143 / 995
What is a project budget?
144 / 995
What is a project schedule?
145 / 995
What is the critical path in project management?
146 / 995
147 / 995
148 / 995
149 / 995
What are the three constraints in project management?
150 / 995
What is a project manager responsible for?
151 / 995
What is the difference between a project and a program?
152 / 995
153 / 995
154 / 995
What is the purpose of the project procurement management process?
155 / 995
What is the purpose of the project human resource management process?
156 / 995
What is the purpose of the project communication management process?
157 / 995
What is the purpose of the project cost management process?
158 / 995
What is the purpose of the project time management process?
159 / 995
What is the purpose of the project scope management process?
160 / 995
What is the purpose of the project integration management process?
161 / 995
What is the purpose of the project quality management process?
162 / 995
What is the purpose of the project risk management process?
163 / 995
What is the purpose of the project resource management process?
164 / 995
What is the purpose of the project stakeholder engagement process?
165 / 995
What is the purpose of the project lessons learned process?
166 / 995
What is the purpose of the project closure process?
167 / 995
What is the purpose of the project change control process?
168 / 995
What is the purpose of the project stakeholder register?
169 / 995
What is the purpose of the project procurement plan?
170 / 995
What is the purpose of the project communication plan?
171 / 995
What is the purpose of the project quality plan?
172 / 995
What is the purpose of the project budget?
173 / 995
What is the purpose of the project schedule?
174 / 995
What is the purpose of the work breakdown structure (WBS)?
175 / 995
What is the purpose of the project risk register?
176 / 995
What is the purpose of the project scope statement?
177 / 995
What is the role of the project sponsor?
178 / 995
What is the purpose of the project charter?
179 / 995
What is a key benefit of using project management processes and techniques?
180 / 995
What does the acronym PMP stand for?
181 / 995
What is the primary role of a project manager?
182 / 995
183 / 995
184 / 995
Which of the following is NOT an output of the Control Risks process?
185 / 995
Which of the following is NOT a tool or technique used in the Control Risks process?
186 / 995
Which of the following is NOT an input to the Control Risks process?
187 / 995
Which of the following is NOT an output of the Control Communications process?
188 / 995
Which of the following is NOT a tool or technique used in the Control Communications process?
189 / 995
Which of the following is NOT an input to the Control Communications process?
190 / 995
Which of the following is NOT an output of the Control Resources process?
191 / 995
Which of the following is NOT a tool or technique used in the Control Resources process?
192 / 995
Which of the following is NOT an input to the Control Resources process?
193 / 995
Which of the following is NOT an output of the Control Quality process?
194 / 995
Which of the following is NOT a tool or technique used in the Control Quality process?
195 / 995
Which of the following is NOT an input to the Control Quality process?
196 / 995
Which of the following is NOT an output of the Control Cost process?
197 / 995
Which of the following is NOT a tool or technique used in the Control Cost process?
198 / 995
Which of the following is NOT an input to the Control Cost process?
199 / 995
Which of the following is NOT an output of the Control Schedule process?
200 / 995
Which of the following is NOT a tool or technique used in the Control Schedule process?
201 / 995
Which of the following is NOT an input to the Control Schedule process?
202 / 995
Which of the following is NOT an output of the Control Scope process?
203 / 995
Which of the following is NOT an input to the Control Scope process?
204 / 995
Which of the following is NOT a tool or technique used in the Control Scope process?
205 / 995
Which of the following is NOT an output of the Create WBS process?
206 / 995
Which of the following is NOT an input to the Create WBS process?
207 / 995
Which of the following is NOT an output of the Define Scope process?
208 / 995
Which of the following is NOT an input to the Define Scope process?
209 / 995
Which of the following is NOT a tool or technique used in the Collect Requirements process?
210 / 995
Which of the following is NOT a technique used in the Define Scope process?
211 / 995
Which of the following is NOT a component of the project management plan?
212 / 995
Which of the following is NOT a tool or technique used in the Plan Scope Management process?
213 / 995
Which of the following is NOT an input to the Develop Project Charter process?
214 / 995
215 / 995
216 / 995
217 / 995
What is the purpose of a project change request?
218 / 995
219 / 995
What is the purpose of a project closure process?
220 / 995
What is the purpose of a lessons learned document?
221 / 995
222 / 995
What is the purpose of a project budget?
223 / 995
224 / 995
What is the purpose of a cost baseline?
225 / 995
226 / 995
227 / 995
What is the purpose of a cost management plan?
228 / 995
229 / 995
What is the purpose of a resource management plan?
230 / 995
231 / 995
232 / 995
233 / 995
234 / 995
235 / 995
236 / 995
What is the definition of a work breakdown structure (WBS)?
237 / 995
238 / 995
What is a project stakeholder?
239 / 995
240 / 995
What is the definition of a project constraint?
241 / 995
What is the purpose of a stakeholder analysis?
242 / 995
243 / 995
What is the critical path method (CPM)?
244 / 995
Which of the following is a tool and technique used in the Control Cost process?
245 / 995
246 / 995
Which of the following is an input to the Control Cost process?
247 / 995
Which of the following is a tool and technique used in the Control Schedule process?
248 / 995
249 / 995
Which of the following is an input to the Control Scope process?
250 / 995
Which of the following is a tool and technique used in the Validate Scope process?
251 / 995
Which of the following is an output of the Validate Scope process?
252 / 995
Which of the following is NOT an output of the Perform Integrated Change Control process?
253 / 995
Which of the following is an input to the Perform Integrated Change Control process?
254 / 995
Which of the following is a tool and technique used in the Monitor and Control Project Work process?
255 / 995
Which of the following is NOT an input to the Monitor and Control Project Work process?
256 / 995
Which of the following is an input to the Direct and Manage Project Work process?
257 / 995
Which of the following is a tool and technique used in the Develop Project Management Plan process?
258 / 995
Which of the following is NOT an input to the Develop Project Management Plan process?
259 / 995
Which of the following is an input to the Develop Project Charter process?
260 / 995
Which of the following is a tool and technique used in the Close Project or Phase process?
261 / 995
Which of the following is NOT an input to the Close Project or Phase process?
262 / 995
Which of the following is a tool and technique used in the Control Stakeholder Engagement process?
263 / 995
Which of the following is an output of the Control Stakeholder Engagement process?
264 / 995
Which of the following is NOT an output of the Conduct Procurements process?
265 / 995
Which of the following is an input to the Conduct Procurements process?
266 / 995
Which of the following is an output of the Plan Risk Responses process?
267 / 995
Which of the following is a tool and technique used in the Plan Risk Responses process?
268 / 995
Which of the following is an output of the Perform Qualitative Risk Analysis process?
269 / 995
Which of the following is NOT an output of the Perform Quantitative Risk Analysis process?
270 / 995
Which of the following is a tool and technique used in the Collect Requirements process?
271 / 995
Which of the following is an input to the Control Quality process?
272 / 995
Which of the following is NOT a process in the Project Integration Management knowledge area?
273 / 995
What does PMP stand for?
274 / 995
What is the primary output of the Implement Risk Responses process?
275 / 995
What is the primary output of the Plan Risk Responses process?
276 / 995
Which of the following is not a tool or technique used in the process of Perform Quantitative Risk Analysis?
277 / 995
What is the formula to calculate the actual cost (AC) using the bottom-up method?
278 / 995
What is the formula to calculate the earned value (EV) using the bottom-up method?
279 / 995
What is the formula to calculate the planned value (PV) using the bottom-up method?
280 / 995
What is the formula to calculate the schedule variance (SV) using the bottom-up method?
281 / 995
What is the formula to calculate the cost variance (CV) using the bottom-up method?
282 / 995
What is the formula to calculate the variance at completion (VAC) using the bottom-up method?
283 / 995
What is the formula to calculate the estimate to complete (ETC) using the bottom-up method?
284 / 995
What is the formula to calculate the estimate at completion (EAC) using the bottom-up method?
285 / 995
What is the formula to calculate the actual cost (AC)?
286 / 995
What is the formula to calculate the earned value (EV)?
287 / 995
What is the formula to calculate the planned value (PV)?
288 / 995
What is the formula to calculate the schedule variance (SV)?
289 / 995
What is the formula to calculate the cost variance (CV)?
290 / 995
What is the formula to calculate the variance at completion (VAC)?
291 / 995
292 / 995
What is the formula to calculate the estimate to complete (ETC)?
293 / 995
What is the formula to calculate the estimate at completion (EAC)?
294 / 995
What is the formula to calculate the schedule performance index (SPI)?
295 / 995
What is the formula to calculate the cost performance index (CPI)?
296 / 995
What type of dependency is characterized by one activity being dependent on the completion of another activity?
297 / 995
What is the primary purpose of the Close Project or Phase process?
298 / 995
What is the primary purpose of the Perform Integrated Change Control process?
299 / 995
Which of the following is a tool or technique used in the process of Define Scope?
300 / 995
What tool or technique is used in the process of Collect Requirements?
301 / 995
What is the primary output of the Develop Project Management Plan process?
302 / 995
Which process group consists of the processes required to establish the scope of the project, refine the objectives, and define the course of action?
303 / 995
What is the first process in project integration management?
304 / 995
Which of the following is a tool or technique used in the Close Project or Phase process?
305 / 995
Which of the following is not an input to the Control Stakeholder Engagement process?
306 / 995
Which of the following is a technique used in the Validate Scope process?
307 / 995
Which of the following is an output of the Monitor and Control Project Work process?
308 / 995
Which of the following is not a tool or technique used in the Perform Integrated Change Control process?
309 / 995
Which of the following is a technique used in the Control Risks process?
310 / 995
Which of the following is an output of the Control Quality process?
311 / 995
312 / 995
313 / 995
Which of the following is an example of a defect repair?
314 / 995
Which of the following is not a tool or technique used in the Validate Scope process?
315 / 995
Which of the following is a technique used in the Perform Integrated Change Control process?
316 / 995
317 / 995
Which of the following is a tool or technique used in the Direct and Manage Project Work process?
318 / 995
319 / 995
Which of the following is an example of a corrective action?
320 / 995
Which of the following is not a tool or technique used in the Control Risks process?
321 / 995
Which of the following is a technique used in the Control Quality process?
322 / 995
Which of the following is an output of the Plan Quality process?
323 / 995
Which of the following is a tool or technique used in the Plan Risk Responses process?
324 / 995
Which of the following is not an input to the Develop Project Charter process?
325 / 995
Which of the following is an example of a preventive action?
326 / 995
Which of the following is a tool or technique used in the Identify Risks process?
327 / 995
Which of the following is not a component of the Cost Baseline?
328 / 995
Which of the following is an example of a project stakeholder?
329 / 995
Which of the following is not a tool or technique used in the Estimate Activity Durations process?
330 / 995
Which of the following is an output of the Perform Integrated Change Control process?
331 / 995
Which of the following is a technique used in the Manage Quality process?
332 / 995
Which of the following is not a type of dependency?
333 / 995
Which of the following is an input to the Define Scope process?
334 / 995
Which of the following is a tool used for identifying and documenting project risks?
335 / 995
Which of the following is not a project management process group?
336 / 995
What is the purpose of a lessons learned log?
337 / 995
What is the purpose of a kickoff meeting?
338 / 995
What is the purpose of a lessons learned meeting?
339 / 995
340 / 995
341 / 995
342 / 995
What is the purpose of a change request form?
343 / 995
What is the purpose of a risk response plan?
344 / 995
What is the purpose of a quality control process?
345 / 995
What is the purpose of a requirements management plan?
346 / 995
347 / 995
348 / 995
349 / 995
350 / 995
351 / 995
352 / 995
353 / 995
What is the purpose of a stakeholder management plan?
354 / 995
355 / 995
356 / 995
What is the purpose of a lessons learned register?
357 / 995
What is the purpose of a communication management plan?
358 / 995
What is the purpose of a change control board?
359 / 995
360 / 995
361 / 995
362 / 995
363 / 995
364 / 995
365 / 995
Which tool is used for identifying stakeholders and their interests?
366 / 995
What is the project management triangle?
367 / 995
What is the definition of a project risk?
368 / 995
369 / 995
What is the definition of a project assumption?
370 / 995
371 / 995
372 / 995
373 / 995
374 / 995
375 / 995
376 / 995
377 / 995
378 / 995
379 / 995
380 / 995
381 / 995
382 / 995
What is the definition of a project deliverable?
383 / 995
What is the formula to calculate the schedule performance index (SPI) of a project?
384 / 995
385 / 995
What is the main purpose of a project communication plan?
386 / 995
What is the main purpose of a project management plan?
387 / 995
What is the formula to calculate the cost performance index (CPI) of a project?
388 / 995
What does the term 'float' refer to in project scheduling?
389 / 995
What is the definition of project scope?
390 / 995
391 / 995
What is the formula to calculate the planned value (PV) of a project?
392 / 995
What is the main purpose of a project charter?
393 / 995
394 / 995
Which process group is responsible for defining and controlling project costs?
395 / 995
What is the first step in project scope management?
396 / 995
397 / 995
Which of the following is not a tool or technique used in the Control Stakeholder Engagement process?
398 / 995
Which of the following is not an input to the Plan Quality Management process?
399 / 995
Which of the following is not a characteristic of a project constraint?
400 / 995
Which of the following is not a tool or technique used in the Control Procurements process?
401 / 995
Which of the following processes is not part of the Project Human Resource Management knowledge area?
402 / 995
403 / 995
404 / 995
Which of the following is not an input to the Plan Cost Management process?
405 / 995
Which of the following is not a characteristic of a project sponsor?
406 / 995
407 / 995
Which of the following processes is part of the Project Cost Management knowledge area?
408 / 995
Which of the following is not an output of the Manage Stakeholder Engagement process?
409 / 995
410 / 995
Which of the following is not an input to the Plan Schedule Management process?
411 / 995
Which of the following is not a characteristic of a project team?
412 / 995
Which of the following is not a tool or technique used in the Control Communications process?
413 / 995
Which of the following processes is not part of the Project Stakeholder Management knowledge area?
414 / 995
415 / 995
Which of the following is not a tool or technique used in the Perform Quality Assurance process?
416 / 995
Which of the following is not an input to the Plan Risk Management process?
417 / 995
Which of the following is not a characteristic of a project manager?
418 / 995
Which of the following is not a tool or technique used in the Estimate Costs process?
419 / 995
Which of the following processes is part of the Project Time Management knowledge area?
420 / 995
Which of the following is not an input to the Close Project or Phase process?
421 / 995
Which of the following is not a tool or technique used in the Plan Scope Management process?
422 / 995
423 / 995
Which of the following is not a characteristic of a project?
424 / 995
Which of the following is not a tool or technique used in the Control Quality process?
425 / 995
Which of the following processes is not part of the Project Integration Management knowledge area?
426 / 995
What is a lesson learned?
427 / 995
What is a project closure?
428 / 995
What is a phase gate?
429 / 995
What is a project life cycle?
430 / 995
What is a project team?
431 / 995
What is a project sponsor?
432 / 995
What is a project manager?
433 / 995
What is a stakeholder management plan?
434 / 995
What is a procurement management plan?
435 / 995
What is a resource management plan?
436 / 995
What is a quality management plan?
437 / 995
What is a communication management plan?
438 / 995
What is the purpose of perform integrated change control?
439 / 995
What is a change request?
440 / 995
What is a risk register?
441 / 995
What is a risk?
442 / 995
What is a critical path?
443 / 995
444 / 995
What is a work breakdown structure (WBS)?
445 / 995
What is a project management plan?
446 / 995
What is a stakeholder register?
447 / 995
What is a project charter?
448 / 995
449 / 995
What is a portfolio?
450 / 995
What is a program?
451 / 995
What is project management?
452 / 995
What is a project?
453 / 995
Which MPM provides better performance for sites with a large number of dynamic requests?
454 / 995
Which MPM supports the use of multiple processes?
455 / 995
Which MPM is recommended for sites with a small number of requests and low memory requirements?
456 / 995
Which MPM supports the use of threads for handling connections?
457 / 995
Which MPM supports the use of both threads and forked child processes?
458 / 995
Which MPM is recommended for sites that require higher levels of security and isolation?
459 / 995
Which MPM is compatible with mod_mpm_itk?
460 / 995
Which MPM supports the use of per-child processes?
461 / 995
Which MPM is recommended for development and debugging purposes?
462 / 995
Which MPM is an alternative to the Prefork MPM?
463 / 995
Which MPM creates separate processes for each request?
464 / 995
Which MPM supports the ability to run virtual hosts under different user accounts?
465 / 995
Which MPM provides better performance for sites with a large amount of static content?
466 / 995
Which MPM can handle more simultaneous requests with fewer resources?
467 / 995
Which MPM is considered the most advanced MPM for Apache?
468 / 995
Which MPM supports the Event MPM threading mode?
469 / 995
Which MPM provides better performance for high-traffic websites with a large number of idle connections?
470 / 995
Which MPM is not recommended for high-traffic websites?
471 / 995
Which MPM has better memory management and is more efficient with threaded models?
472 / 995
Which MPM allows running each virtual host under a separate UID and GID?
473 / 995
Which MPM provides better security by isolating each virtual host in its own environment?
474 / 995
Which MPM is recommended for high-performance sites?
475 / 995
Which MPM allows handling more concurrent connections with fewer resources?
476 / 995
What does MPM Event provide?
477 / 995
What does MPM Worker provide?
478 / 995
What does MPM Prefork provide?
479 / 995
Which MPM is the default choice for Apache HTTP Server?
480 / 995
What does MPM stand for?
481 / 995
482 / 995
What is the purpose of the project risk assessment?
483 / 995
What is the purpose of the project scope management plan?
484 / 995
485 / 995
What is the purpose of the project risk management plan?
486 / 995
What is the purpose of the project integration management plan?
487 / 995
What is the definition of a project objective?
488 / 995
What is the purpose of the project stakeholder analysis?
489 / 995
What is the purpose of the project issue log?
490 / 995
491 / 995
What is the purpose of the project resource management plan?
492 / 995
What is the purpose of the project lessons learned?
493 / 995
What is the definition of a project issue?
494 / 995
What is the purpose of the project change management plan?
495 / 995
496 / 995
497 / 995
498 / 995
What is the purpose of the project quality management plan?
499 / 995
500 / 995
501 / 995
502 / 995
503 / 995
504 / 995
505 / 995
506 / 995
What is the difference between a risk and an issue?
507 / 995
508 / 995
What is the best definition of a project stakeholder?
509 / 995
510 / 995
511 / 995
512 / 995
What is the purpose of the project stakeholders register?
513 / 995
What is the purpose of project procurement management?
514 / 995
What is the purpose of project risk management?
515 / 995
What is the purpose of the project communications management plan?
516 / 995
What is the purpose of project human resource management?
517 / 995
What is the purpose of project quality management?
518 / 995
519 / 995
What is the purpose of project cost management?
520 / 995
What is the purpose of project time management?
521 / 995
522 / 995
What is the purpose of project scope management?
523 / 995
What is the primary goal of project integration management?
524 / 995
525 / 995
526 / 995
What is the primary goal of project procurement management?
527 / 995
528 / 995
529 / 995
What is the primary goal of project human resource management?
530 / 995
531 / 995
532 / 995
What is the primary goal of project cost management?
533 / 995
What is the primary goal of project time management?
534 / 995
What is the purpose of the change control process?
535 / 995
536 / 995
What is the purpose of project stakeholder management?
537 / 995
What is the purpose of the project management plan?
538 / 995
What is the primary goal of project scope management?
539 / 995
540 / 995
What is the first process in project quality management?
541 / 995
What is the last process in project cost management?
542 / 995
What is the first process in project cost management?
543 / 995
What is the last process in project schedule management?
544 / 995
What is the first process in project schedule management?
545 / 995
What is the last process in project scope management?
546 / 995
What is the first process in project scope management?
547 / 995
What is the last process in project integration management?
548 / 995
549 / 995
What is the last process in project stakeholder management?
550 / 995
What is the first process in project stakeholder management?
551 / 995
What is the last process in project procurement management?
552 / 995
What is the first process in project procurement management?
553 / 995
What is the last process in project risk management?
554 / 995
What is the first process in project risk management?
555 / 995
What is the last process in project communications management?
556 / 995
What is the first process in project communications management?
557 / 995
What is the last process in project resource management?
558 / 995
What is the first process in project resource management?
559 / 995
What is the last process in project quality management?
560 / 995
561 / 995
562 / 995
563 / 995
564 / 995
565 / 995
566 / 995
567 / 995
568 / 995
569 / 995
What is the purpose of a project quality inspection?
570 / 995
What is the purpose of a project status update?
571 / 995
What is the purpose of a project kickoff event?
572 / 995
What is the purpose of a project stakeholder meeting?
573 / 995
What is the purpose of a project risk review?
574 / 995
What is the purpose of a project quality audit?
575 / 995
What is the purpose of a project status meeting?
576 / 995
577 / 995
What is the purpose of a project dashboard?
578 / 995
579 / 995
What is the purpose of a project kickoff meeting?
580 / 995
581 / 995
582 / 995
583 / 995
What is the purpose of a project change control process?
584 / 995
585 / 995
586 / 995
587 / 995
588 / 995
589 / 995
What is a project baseline?
590 / 995
591 / 995
592 / 995
593 / 995
594 / 995
595 / 995
What is a project scope?
596 / 995
597 / 995
598 / 995
599 / 995
Which of the following is a characteristic of a project?
600 / 995
Which of the following is a tool or technique used in the Control Quality process?
601 / 995
Which of the following is an output of the Direct and Manage Project Work process?
602 / 995
Which of the following is an input to the Control Risks process?
603 / 995
Which of the following is an output of the Control Costs process?
604 / 995
Which of the following is an output of the Control Schedule process?
605 / 995
606 / 995
607 / 995
Which of the following is an output of the Plan Stakeholder Engagement process?
608 / 995
Which of the following is an output of the Identify Stakeholders process?
609 / 995
Which of the following is an output of the Plan Communications Management process?
610 / 995
Which of the following is a tool or technique used in the Perform Quality Assurance process?
611 / 995
Which of the following is an output of the Plan Risk Management process?
612 / 995
Which of the following is an input to the Estimate Activity Durations process?
613 / 995
Which of the following is an output of the Plan Procurement Management process?
614 / 995
615 / 995
616 / 995
617 / 995
Which of the following is an output of the Plan Quality Management process?
618 / 995
Which of the following is an input to the Control Communications process?
619 / 995
620 / 995
621 / 995
622 / 995
Which of the following is an output of the Control Procurements process?
623 / 995
624 / 995
Which of the following is an output of the Develop Project Team process?
625 / 995
Which of the following is a characteristic of a matrix organizational structure?
626 / 995
627 / 995
Which of the following is a tool or technique used in the Perform Integrated Change Control process?
628 / 995
629 / 995
What is the primary benefit of using a project management methodology?
630 / 995
What does the term 'earned value' refer to in project management?
631 / 995
What is the purpose of the resource management plan?
632 / 995
Which process group includes the creation of a project charter?
633 / 995
What is the purpose of the change control board?
634 / 995
635 / 995
What does the term 'variance' refer to in project management?
636 / 995
What is the purpose of the lessons learned register?
637 / 995
Which process group includes the finalizing of a project?
638 / 995
What is the purpose of the procurement management plan?
639 / 995
640 / 995
What does the term 'baseline' refer to in project management?
641 / 995
What is the purpose of the change log?
642 / 995
Which process group includes the development of a project budget?
643 / 995
What is the purpose of the quality management plan?
644 / 995
645 / 995
What does the term 'critical path' refer to in project management?
646 / 995
What is the purpose of the issue log?
647 / 995
Which process group includes the monitoring and controlling of a project?
648 / 995
What is the purpose of the communications management plan?
649 / 995
650 / 995
What does the term 'float' refer to in project management?
651 / 995
What is the purpose of the stakeholder register?
652 / 995
Which process group includes the initiation of a project?
653 / 995
What is the purpose of the risk register?
654 / 995
655 / 995
What is the primary output of the scope verification process?
656 / 995
657 / 995
Which process group consists of the processes required to complete the work defined in the project management plan?
658 / 995
659 / 995
660 / 995
Which of the following is NOT a tool or technique used in the Control Procurements process?
661 / 995
Which of the following is an output of the Report Performance process?
662 / 995
Which of the following is a tool used in the Develop Schedule process?
663 / 995
Which of the following is NOT an input to the Identify Risks process?
664 / 995
665 / 995
Which of the following is NOT a tool or technique used in the Plan Procurement Management process?
666 / 995
Which of the following is an output of the Control Communications process?
667 / 995
Which of the following is NOT a tool or technique used in the Plan Risk Management process?
668 / 995
Which of the following is a tool used in the Estimate Costs process?
669 / 995
670 / 995
Which of the following is NOT a tool or technique used in the Plan Human Resource Management process?
671 / 995
672 / 995
Which of the following is a tool used in the Develop Project Team process?
673 / 995
674 / 995
Which of the following is an output of the Close Project or Phase process?
675 / 995
Which of the following is a tool used in the Conduct Procurements process?
676 / 995
Which of the following is NOT a cost estimating technique?
677 / 995
678 / 995
Which of the following is a tool used in the Validate Scope process?
679 / 995
680 / 995
Which of the following is a tool used in the Control Quality process?
681 / 995
682 / 995
683 / 995
Which of the following is a tool used in the Estimate Activity Durations process?
684 / 995
Which of the following is an input to the Identify Stakeholders process?
685 / 995
Which of the following is NOT a characteristic of a project?
686 / 995
Which of the following is NOT a risk response strategy?
687 / 995
Which of the following is a tool used in the Plan Scope Management process?
688 / 995
What is the primary purpose of a project charter?
689 / 995
Which of the following is NOT a type of project management office?
690 / 995
Which of the following is a tool or technique used in project risk management?
691 / 995
Which of the following is an output of project quality management?
692 / 995
Which of the following is NOT a component of the project scope statement?
693 / 995
Which of the following is an input to project scope management?
694 / 995
Which of the following is the final step in project integration management?
695 / 995
Which of the following is NOT a tool or technique of project time management?
696 / 995
Which of the following is an output of project procurement management?
697 / 995
Which of the following is NOT a type of project organization?
698 / 995
Which of the following is a tool or technique used in project quality management?
699 / 995
Which of the following is an output of project risk management?
700 / 995
701 / 995
Which of the following is an input to project communication management?
702 / 995
Which of the following is NOT a type of constraint in project management?
703 / 995
Which of the following is a tool or technique used in project procurement management?
704 / 995
Which of the following is an output of project stakeholder management?
705 / 995
706 / 995
707 / 995
708 / 995
709 / 995
Which of the following is an input to project integration management?
710 / 995
Which of the following is a tool or technique used in project cost management?
711 / 995
Which of the following is NOT a constraint of project management?
712 / 995
Which of the following is an output of project communication management?
713 / 995
Which of the following is NOT a type of organizational structure?
714 / 995
715 / 995
716 / 995
Which of the following is NOT a responsibility of a project manager?
717 / 995
718 / 995
Which of the following is an output of project scope management?
719 / 995
720 / 995
Which of the following is not a component of the project charter?
721 / 995
Which of the following is not a characteristic of a project manager in a functional organizational structure?
722 / 995
Which of the following is not a technique used in the process of Develop Schedule?
723 / 995
Which of the following is not an input to the process of Estimate Costs?
724 / 995
Which of the following is not a tool or technique used in the process of Define Activities?
725 / 995
Which of the following is not a component of the project scope statement?
726 / 995
Which of the following is not an output of the process of Identify Stakeholders?
727 / 995
728 / 995
Which of the following is not a typical responsibility of the project sponsor?
729 / 995
Which of the following is not a common risk response strategy?
730 / 995
Which of the following is not an input to the process of Direct and Manage Project Work?
731 / 995
Which of the following is not a tool or technique used in the process of Estimate Activity Durations?
732 / 995
Which of the following is not a component of the project management plan?
733 / 995
Which of the following is not an output of the process of Close Procurements?
734 / 995
Which of the following is not a characteristic of a weak matrix organizational structure?
735 / 995
Which of the following is not a typical responsibility of the project manager?
736 / 995
Which of the following is not an output of the process of Control Risks?
737 / 995
Which of the following is not a tool or technique used in the process of Collect Requirements?
738 / 995
Which of the following is not an input to the process of Develop Project Team?
739 / 995
Which of the following is not a characteristic of a project manager in a strong matrix organizational structure?
740 / 995
Which of the following is not a technique used in the process of Control Procurements?
741 / 995
Which of the following is not an input to the process of Identify Risks?
742 / 995
743 / 995
Which of the following is not a constraint that can impact the development of the project schedule?
744 / 995
Which of the following is not an output of the process of Control Quality?
745 / 995
Which of the following is not a characteristic of a functional organizational structure?
746 / 995
747 / 995
748 / 995
Which of the following is not an input to the process of Develop Schedule?
749 / 995
Which of the following is not a tool or technique used in the process of Estimate Costs?
750 / 995
751 / 995
Which of the following is not a primary characteristic of a project?
752 / 995
What is the name of the process in which the project manager and key stakeholders review the project's performance?
753 / 995
Which of the following is NOT a process in the Project Resource Management knowledge area?
754 / 995
What is the purpose of the Control Quality process?
755 / 995
Which of the following is NOT a tool or technique used in the Perform Quality Assurance process?
756 / 995
Which of the following is NOT an input to the Plan Quality Management process?
757 / 995
What is the role of a project manager during the Initiating phase of a project?
758 / 995
Which of the following is NOT a process in the Project Quality Management knowledge area?
759 / 995
What is the purpose of the Control Costs process?
760 / 995
Which of the following is NOT a tool or technique used in the Determine Budget process?
761 / 995
Which of the following is NOT an input to the Estimate Costs process?
762 / 995
What is the role of a project manager during the Closing phase of a project?
763 / 995
Which of the following is NOT a process in the Project Cost Management knowledge area?
764 / 995
What is the purpose of the Estimate Activity Durations process?
765 / 995
Which of the following is NOT a tool or technique used in the Sequence Activities process?
766 / 995
Which of the following is NOT an input to the Define Activities process?
767 / 995
What is the role of a project manager during the Monitoring and Controlling phase of a project?
768 / 995
Which of the following is NOT a process in the Project Time Management knowledge area?
769 / 995
What is the purpose of the Control Scope process?
770 / 995
Which of the following is NOT a tool or technique used in the Define Scope process?
771 / 995
Which of the following is NOT an input to the Plan Scope Management process?
772 / 995
What is the role of a project manager during the Executing phase of a project?
773 / 995
774 / 995
775 / 995
Which of the following is NOT a process in the Project Scope Management knowledge area?
776 / 995
What is the role of a project manager during the Planning phase of a project?
777 / 995
Which of the following is NOT a tool or technique used in the Plan Communications Management process?
778 / 995
779 / 995
780 / 995
Which of the following is NOT a benefit of using a project management methodology?
781 / 995
Which of the following is NOT a tool or technique used in the Develop Project Charter process?
782 / 995
783 / 995
784 / 995
What is a project issue log?
785 / 995
What is the purpose of a project lessons learned document?
786 / 995
What is a project constraint register?
787 / 995
788 / 995
What is a project assumption register?
789 / 995
790 / 995
791 / 995
792 / 995
What is a project dependency?
793 / 995
What is the purpose of a project resource management plan?
794 / 995
795 / 995
796 / 995
What is a project constraint log?
797 / 995
What is the purpose of a project cost management plan?
798 / 995
What is a project assumption log?
799 / 995
What is the purpose of a project quality plan?
800 / 995
What is a project deliverable?
801 / 995
802 / 995
What is a project assumption?
803 / 995
804 / 995
805 / 995
806 / 995
807 / 995
808 / 995
809 / 995
810 / 995
811 / 995
812 / 995
813 / 995
814 / 995
Which of the following is NOT a tool or technique used in the Control Stakeholder Engagement process?
815 / 995
Which of the following is NOT an output of the Control Stakeholder Engagement process?
816 / 995
Which of the following is NOT an input to the Control Stakeholder Engagement process?
817 / 995
818 / 995
Which of the following is NOT an output of the Control Procurements process?
819 / 995
Which of the following is NOT an input to the Control Procurements process?
820 / 995
821 / 995
822 / 995
823 / 995
Which of the following is NOT a tool or technique used in the Plan Risk Responses process?
824 / 995
Which of the following is NOT a tool or technique used in the Perform Quantitative Risk Analysis process?
825 / 995
Which of the following is NOT a tool or technique used in the Perform Qualitative Risk Analysis process?
826 / 995
Which of the following is NOT a tool or technique used in the Identify Risks process?
827 / 995
828 / 995
829 / 995
Which of the following is NOT an output of the Close Project or Phase process?
830 / 995
Which of the following is NOT an output of the Monitor and Control Project Work process?
831 / 995
Which of the following is NOT an output of the Direct and Manage Project Work process?
832 / 995
Which of the following is NOT an output of the Develop Project Management Plan process?
833 / 995
834 / 995
Which of the following is NOT a key benefit of using project management processes and practices?
835 / 995
Which of the following is NOT a tool or technique used in the Close Project or Phase process?
836 / 995
Which of the following is NOT a tool or technique used in the Perform Integrated Change Control process?
837 / 995
Which of the following is NOT a tool or technique used in the Direct and Manage Project Work process?
838 / 995
Which of the following is NOT a tool or technique used in the Develop Project Management Plan process?
839 / 995
Which of the following statements about the project life cycle is TRUE?
840 / 995
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships is known as:
841 / 995
Which of the following is NOT a project management process?
842 / 995
843 / 995
844 / 995
Which of the following is NOT a project management knowledge area?
845 / 995
Which process group involves ensuring that the project is completed and the project deliverables are handed over to the customer?
846 / 995
Which process group involves obtaining formal sign-off on project deliverables?
847 / 995
Which process group involves documenting lessons learned for future projects?
848 / 995
Which process group involves measuring project performance and taking corrective actions?
849 / 995
Which process group involves ensuring that project work is being performed as planned?
850 / 995
Which process group involves reviewing and approving project deliverables?
851 / 995
Which process group involves obtaining approval for project changes?
852 / 995
Which process group involves obtaining final acceptance of the project deliverables?
853 / 995
Which process group involves obtaining feedback from stakeholders?
854 / 995
Which process group involves ensuring that the project meets the defined scope?
855 / 995
Which process group involves obtaining approval to begin the project?
856 / 995
Which process group involves managing project risks?
857 / 995
Which process group involves establishing and maintaining communication with stakeholders?
858 / 995
Which process group involves identifying and documenting project assumptions and constraints?
859 / 995
Which process group involves reviewing and approving changes to the project?
860 / 995
Which process group involves executing the project management plan?
861 / 995
Which process group involves obtaining the necessary resources to complete the project?
862 / 995
Which process group involves creating the project management plan?
863 / 995
Which process group involves developing a detailed project schedule?
864 / 995
Which process group involves creating the project charter?
865 / 995
Which process group involves identifying and documenting project risks?
866 / 995
Which process group involves managing changes to the project scope, schedule, and budget?
867 / 995
Which process group involves obtaining formal acceptance of the completed project deliverables?
868 / 995
Which process group involves ensuring that the project meets the defined quality standards?
869 / 995
Which process group involves tracking, reviewing, and reporting project progress?
870 / 995
Which process group involves managing the project team and stakeholders?
871 / 995
Which process group involves developing a detailed description of the project and product?
872 / 995
Which process group involves formally accepting the completed project deliverables and ensures that the project has met all the stated requirements?
873 / 995
Which process group involves defining and refining project objectives and selecting the best course of action to achieve those objectives?
874 / 995
Which process group involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan?
875 / 995
What is the formula to calculate the Estimate at Completion (EAC) when using the Cost Performance Index (CPI)?
876 / 995
Which of the following is NOT a characteristic of a project team?
877 / 995
Which of the following is a tool or technique used in the Control Risks process?
878 / 995
What is the purpose of the Control Stakeholder Engagement process?
879 / 995
Which of the following is a tool or technique used in the Collect Requirements process?
880 / 995
What is the formula to calculate the Cost Variance (CV)?
881 / 995
What is the primary output of the Control Procurements process?
882 / 995
Which of the following is a tool or technique used in the Plan Scope Management process?
883 / 995
What is the purpose of the Identify Stakeholders process?
884 / 995
Which of the following is NOT a characteristic of a project sponsor?
885 / 995
886 / 995
What is the formula to calculate the Schedule Variance (SV)?
887 / 995
What is the purpose of the Close Procurements process?
888 / 995
889 / 995
What is the primary output of the Validate Scope process?
890 / 995
What is the formula to calculate the Estimate to Complete (ETC) when using the To-Complete Performance Index (TCPI)?
891 / 995
Which of the following is NOT a characteristic of a project manager?
892 / 995
893 / 995
What is the purpose of the Monitor Stakeholder Engagement process?
894 / 995
Which of the following is a tool or technique used in the Define Scope process?
895 / 995
What is the formula to calculate the Cost Performance Index (CPI)?
896 / 995
897 / 995
898 / 995
Which of the following is a tool or technique used in the Develop Schedule process?
899 / 995
What is the formula to calculate the Estimate at Completion (EAC) when using the To-Complete Performance Index (TCPI)?
900 / 995
901 / 995
What is the primary output of the Monitor and Control Project Work process?
902 / 995
What is the formula to calculate the Schedule Performance Index (SPI)?
903 / 995
What is the first process in the Project Integration Management knowledge area?
904 / 995
What is the output of the Plan Risk Management process?
905 / 995
Which of the following is a tool or technique used in the Plan Risk Management process?
906 / 995
What is the purpose of the Plan Risk Management process?
907 / 995
What is the output of the Identify Risks process?
908 / 995
909 / 995
What is the purpose of the Identify Risks process?
910 / 995
What is the output of the Plan Stakeholder Engagement process?
911 / 995
Which of the following is a tool or technique used in the Plan Stakeholder Engagement process?
912 / 995
What is the purpose of the Plan Stakeholder Engagement process?
913 / 995
What is the output of the Identify Stakeholders process?
914 / 995
Which of the following is a tool or technique used in the Identify Stakeholders process?
915 / 995
916 / 995
What is the output of the Close Project or Phase process?
917 / 995
918 / 995
919 / 995
What is the output of the Perform Integrated Change Control process?
920 / 995
921 / 995
922 / 995
What is the output of the Monitor and Control Project Work process?
923 / 995
Which of the following is a tool or technique used in the Monitor and Control Project Work process?
924 / 995
925 / 995
What is the output of the Direct and Manage Project Work process?
926 / 995
927 / 995
928 / 995
What is the output of the Develop Project Management Plan process?
929 / 995
Which of the following is a tool or technique used in the Develop Project Management Plan process?
930 / 995
931 / 995
932 / 995
What is the output of the Develop Project Charter process?
933 / 995
Which of the following is a tool or technique used in the Develop Project Charter process?
934 / 995
935 / 995
What is the first process in the project integration management?
936 / 995
Which of the following is NOT a tool or technique used in the Monitor and Control Project Work process?
937 / 995
938 / 995
Which of the following is an input to the Develop Project Management Plan process?
939 / 995
Which of the following is NOT a tool or technique used in the Estimate Costs process?
940 / 995
941 / 995
Which of the following is an input to the Develop Schedule process?
942 / 995
943 / 995
Which of the following is an output of the Collect Requirements process?
944 / 995
945 / 995
946 / 995
947 / 995
Which of the following is an input to the Validate Scope process?
948 / 995
949 / 995
Which of the following is an output of the Control Risks process?
950 / 995
Which of the following is an input to the Develop Project Team process?
951 / 995
Which of the following is NOT a tool or technique used in the Plan Stakeholder Engagement process?
952 / 995
Which of the following is an output of the Monitor Communications process?
953 / 995
Which of the following is an input to the Monitor and Control Project Work process?
954 / 995
955 / 995
Which of the following is an output of the Conduct Procurements process?
956 / 995
Which of the following is an input to the Acquire Resources process?
957 / 995
The purpose of the Plan Risk Responses process is to: